Stucco Calculator: How Many Bags of Stucco Do I Need?

Enter each wall below to get 80 lb bags of base coat and finish coat stucco, metal lath for a 3-coat system, or cement and sand to mix your own. Re-coating old stucco too.

One-Click Project Starters

Fills Zone A

Walls

1 zone

System

3-coat goes over wood framing with metal lath. 2-coat goes straight onto block or concrete. Re-coat is a new finish coat over sound existing stucco.

Base Coat Thickness (total)

Standard is ¾ in for 3-coat (scratch + brown) and ½ in for 2-coat. Uneven walls need more.

Finish Coat

1/8 in suits smooth and sand finishes; heavier textures need about 1/4 in.

10%
0%10%20%

Stucco is lost on the hawk, the ground and uneven walls. 10% is typical.

Cost Estimator (optional)

$

Cost uses base and finish coat bags. Excludes lath, trim, delivery and sales tax.

Don’t know local pricing? Find prices near you

Project Results

1 zone

Base Coat

0 × 80 lb bags

3-coat over lath · incl. 10% waste

Finish Coat

0 × 80 lb bags

1/8 in finish coat

Wall Area

0 sq ft

After doors and windows

Or Mix Your Own Base

0 × 94 lb portland cement

Metal Lath

0 sheets

27 × 96 in sheets, lapped

The link reopens this exact estimate: every zone, setting and price.

Collect estimates from several calculators on one page to print or send.

Spot a mistake? Report a correction

Estimates only. Coverage uses QUIKRETE's published yields for 80 lb bags: 3-coat base about 128 sq ft per 10 bags, 2-coat about 192, finish coat about 720 sq ft per 10 bags at 1/8 in. Rough walls and thick textures use more. Mix-your-own amounts use Hedberg's published site-mix rates (sand counted at 11 lb per shovel).

Field Guide

How Much Stucco Do I Need?

Quick answer: For 3-coat stucco, one 80 lb bag of base coat covers about 13 sq ft and a bag of finish coat about 72 sq ft at 1/8 in. A 40 × 9 ft wall less 45 sq ft of windows (315 sq ft) takes 28 bags of base coat, 5 of finish and 21 sheets of lath with 10% waste. To mix your own base coats instead, that wall takes about 8 bags of portland cement, 4 bags of masonry cement and 1.4 tons of sand.

Stucco goes on in coats: a base coat to build up the thickness, then a thin finish coat for color and texture. Measure the wall area, then work out each coat from its coverage per bag.

1. How to Calculate Stucco (The Math Explained)

Here's the exact process this calculator uses, with one wall 40 ft long and 9 ft high, with 45 sq ft of windows, in 3-coat stucco as the example.

  1. 1

    Find the wall area

    Multiply the length by the height, take off the openings, then add waste.

    Area = 40 × 9 − 45 = 315 sq ft
    With 10% waste = 346.5 sq ft
  2. 2

    Base coat

    3-coat stucco (3/8 in scratch + 3/8 in brown coat) takes about 782 bags per 10,000 sq ft; 2-coat over block about 521.

    Base = 346.5 × 0.0782 = 27.1 → 28 bags
  3. 3

    Finish coat and lath

    A 1/8 in finish takes about 139 bags per 10,000 sq ft. Each lapped 27 × 96 in lath sheet covers about 17 sq ft.

    Finish = 346.5 × 0.0139 = 4.8 → 5 bags
    Lath   = 346.5 ÷ 16.97 = 20.4 → 21 sheets

2. 3-Coat vs 2-Coat Stucco

Stucco systems
SystemGoes overCoatsBase bags per 100 sq ft
3-coatWood framing or sheathing, with paper and metal lath3/8 in scratch + 3/8 in brown + finish7.8
2-coatConcrete block, poured concrete1/2 in brown + finish5.2

Finish coat: about 1.4 bags per 100 sq ft at 1/8 in (smooth, sand and light textures), or 2.8 at 1/4 in (heavy dash and lace textures). Coverage is QUIKRETE's published yield for 80 lb bags.

3. Stucco Tips

  • Wet-cure every coat. Mist each coat for a couple of days so it cures slowly; stucco that dries too fast cracks.

  • Wait between coats. Score the scratch coat and let it firm up before the brown coat; let the brown coat cure (often 7 days) before the finish.

  • Don't forget the trim. Weep screed at the bottom of framed walls, corner bead and control joints are bought by the piece.

Pro tip: patching vs whole walls

For patches and small walls, bagged base coat and finish from a home center are easiest. For a whole house, a stucco supplier will deliver base, finish, lath and trim on a pallet, often for less.

4. Frequently Asked Questions

How many bags of stucco do I need per square foot?

For a 3-coat system (3/4 in of base coat over lath), plan on about one 80 lb bag of base coat per 13 sq ft and one bag of finish coat per 72 sq ft at 1/8 in. A 2-coat system over block uses about one base bag per 19 sq ft.

How much stucco do I need for 1,000 square feet?

For 3-coat stucco over lath: about 79 bags of base coat, 14 bags of finish coat and 59 sheets of lath, before waste. With 10% waste that is 87 base, 16 finish and 65 lath sheets. Over block (2-coat), the base coat drops to about 58 bags with waste.

What is the difference between 3-coat and 2-coat stucco?

3-coat stucco is a scratch coat and a brown coat (about 3/8 in each) over metal lath on wood framing, then a finish coat. 2-coat stucco skips the scratch coat because block and concrete already give the stucco something to grip, so a single 1/2 in brown coat and the finish coat are enough.

How many square feet does a sheet of metal lath cover?

A standard 27 × 96 in sheet is 18 sq ft, but sheets overlap about 1 in at the sides and 2 in at the ends, so each covers about 17 sq ft of wall.

How do I measure a house for stucco?

Add up the length of every wall around the house (the perimeter) and multiply by the wall height. Add each gable end as a triangle, width × height ÷ 2 (enter it as an extra wall), then take off doors (about 21 sq ft) and windows (about 15 sq ft). Add 10% for waste.

How much stucco do I need to re-coat old stucco?

A new finish (color) coat over sound stucco takes about 1 bag of 80 lb finish coat per 72 sq ft at 1/8 in, or per 36 sq ft at 1/4 in. Choose Re-coat existing in the calculator. Repair cracks and loose areas first.

Can you put stucco over painted stucco?

Yes, but new stucco won't bond well to paint or sealer on its own. Clean the wall and apply a bonding agent first (or remove loose paint), then the new coat. Over bare, sound stucco, dampen the wall instead.

How much cement and sand do I need to mix my own stucco?

A common site mix (Hedberg's published rates) is, per 90 sq ft of each 3/8 in base coat, 1 bag of portland cement, ½ bag of Type N masonry cement and about 28–36 shovels of sand. The finish coat takes about 1 bag of white portland and 2 × 100 lb bags of silica sand per 110 sq ft. The calculator works these out next to the premixed bags.

Does this include EIFS or one-coat stucco?

No. EIFS (foam board with a thin finish) and one-coat fiber stucco systems have their own coverage rates; use the manufacturer's chart for those. This calculator covers traditional cement stucco.